Bid Tabulations
Letting of
06/30/2009
LA DOTD Headquarters
| Lead Project: 006-30-0042 | |
| Parish: Jefferson | |
| Routes: LA 48 | |
| Description: JEFFERSON HIGHWAY (HUEY P. LONG BRIDGE - WILLIAMS BLVD.) | |
| Type Const: GRAD, CLASS II BC, COLD PLANING ACP, SUPERPAVE ACP, PAVEMENT PATCHING AND WIDENING, AND RELATED WORK. | |
| Estimated Construction Cost: $5,193,402.79 | |
| Maximum Number of Days Allowed for Construction: 365 | |
| Calculated Daily User Cost: $3,000.00 | |
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time |
Total Bid |
|---|---|---|---|---|---|
| 1 | 06276 | Barriere Construction Co., LLC | $4,949,982.25 | 135 | $5,354,982.25 |
| 2 | 02179 | Boh Bros. Construction Co., LLC. | $5,844,680.85 | 200 | $6,444,680.85 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Barriere Construction Co., LLC |
- 2 - Boh Bros. Construction Co., LLC. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 5,000.00 | 5,000.00 | 500.00 | 500.00 |
| 0002 | 202-02-06060 | Removal of Concrete Catch Basin | 1 | EACH | 1,300.00 | 1,300.00 | 1,000.00 | 1,000.00 |
| 0003 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 2,000 | LNFT | 11.00 | 22,000.00 | 20.00 | 40,000.00 |
| 0004 | 202-02-26300 | Removal of Median / Island | 901 | SQYD | 10.00 | 9,010.00 | 10.00 | 9,010.00 |
| 0005 | 202-02-36000 | Removal of Railroad Grade Crossing | 1 | EACH | 30,000.00 | 30,000.00 | 7,000.00 | 7,000.00 |
| 0006 | 203-07-00100 | Borrow (Vehicular Measurement) | 700 | CUYD | 10.00 | 7,000.00 | 20.00 | 14,000.00 |
| 0007 | 302-02-06000 | Class II Base Course (12" Thick) | 3 | SQYD | 60.00 | 180.00 | 300.00 | 900.00 |
| 0008 | 502-01-00100 | Superpave Asphaltic Concrete | 24,435 | TON | 89.00 | 2,174,715.00 | 100.00 | 2,443,500.00 |
| 0009 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 2,557 | TON | 89.00 | 227,573.00 | 125.00 | 319,625.00 |
| 0010 | 509-01-00100 | Cold Planing Asphaltic Pavement | 234,252 | SQYD | 1.00 | 234,252.00 | 3.00 | 702,756.00 |
| 0011 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -9,169 | CUYD | 10.00 | -91,690.00 | 15.00 | -137,535.00 |
| 0012 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 7,500 | SQYD | 60.00 | 450,000.00 | 50.00 | 375,000.00 |
| 0013 | 510-02-00100 | Pavement Widening | 834 | SQYD | 45.00 | 37,530.00 | 100.00 | 83,400.00 |
| 0014 | 701-14-00100 | Cleaning Existing Pipes | 2,760 | LNFT | 15.50 | 42,780.00 | 15.00 | 41,400.00 |
| 0015 | 702-02-00001 | Manhole (Remove and Replace Frame and Cover) | 2 | EACH | 1,300.00 | 2,600.00 | 1,400.00 | 2,800.00 |
| 0016 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 5,000.00 | 5,000.00 | 5,500.00 | 5,500.00 |
| 0017 | 702-04-00100 | Adjusting Manholes | 9 | EACH | 1,500.00 | 13,500.00 | 1,200.00 | 10,800.00 |
| 0018 | 702-04-00200 | Adjusting Catch Basins | 3 | EACH | 1,800.00 | 5,400.00 | 2,000.00 | 6,000.00 |
| 0019 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 162 | SQYD | 130.00 | 21,060.00 | 150.00 | 24,300.00 |
| 0020 | 706-04-00100 | Handicapped Curb Ramps | 20 | EACH | 2,100.00 | 42,000.00 | 2,800.00 | 56,000.00 |
| 0021 | 707-01-00200 | Concrete Curb (Barrier) | 950 | LNFT | 65.00 | 61,750.00 | 30.00 | 28,500.00 |
| 0022 | 707-03-00100 | Combination Concrete Curb and Gutter | 2,000 | LNFT | 100.00 | 200,000.00 | 60.00 | 120,000.00 |
| 0023 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 400,000.00 | 400,000.00 | 570,000.00 | 570,000.00 |
| 0024 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 3,356 | LNFT | 0.20 | 671.20 | 0.20 | 671.20 |
| 0025 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 1,398 | LNFT | 0.60 | 838.80 | 0.60 | 838.80 |
| 0026 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 24.89 | MILE | 130.00 | 3,235.70 | 350.00 | 8,711.50 |
| 0027 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 12.53 | MILE | 350.00 | 4,385.50 | 380.00 | 4,761.40 |
| 0028 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 25.53 | MILE | 450.00 | 11,488.50 | 400.00 | 10,212.00 |
| 0029 | 713-05-00100 | Temporary Pavement Legends & Symbols (Arrow) | 51 | EACH | 20.00 | 1,020.00 | 40.00 | 2,040.00 |
| 0030 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 22 | EACH | 20.00 | 440.00 | 40.00 | 880.00 |
| 0031 | 713-05-00500 | Temporary Pavement Legends & Symbols (SCHOOL CROSSING) | 12 | EACH | 25.00 | 300.00 | 50.00 | 600.00 |
| 0032 | 717-01-00100 | Seeding | 6 | LB | 1.00 | 6.00 | 20.00 | 120.00 |
| 0033 | 718-01-00100 | Fertilizer | 200 | LB | 1.00 | 200.00 | 1.00 | 200.00 |
| 0034 | 726-01-00100 | Bedding Material | 5 | CUYD | 65.00 | 325.00 | 70.00 | 350.00 |
| 0035 | 727-01-00100 | Mobilization | 1 | LUMP | 425,000.00 | 425,000.00 | 580,000.00 | 580,000.00 |
| 0036 | 731-02-00100 | Reflectorized Raised Pavement Markers | 2,386 | EACH | 5.25 | 12,526.50 | 5.70 | 13,600.20 |
| 0037 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 3,356 | LNFT | 1.15 | 3,859.40 | 1.25 | 4,195.00 |
| 0038 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 1,398 | LNFT | 4.75 | 6,640.50 | 5.00 | 6,990.00 |
| 0039 | 732-02-01000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 40 mil) | 25.53 | MILE | 1,575.00 | 40,209.75 | 1,600.00 | 40,848.00 |
| 0040 | 732-03-01000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 40 mil) | 12.53 | MILE | 700.00 | 8,771.00 | 700.00 | 8,771.00 |
| 0041 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 37 | EACH | 200.00 | 7,400.00 | 200.00 | 7,400.00 |
| 0042 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 24 | EACH | 200.00 | 4,800.00 | 200.00 | 4,800.00 |
| 0043 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 22 | EACH | 205.00 | 4,510.00 | 200.00 | 4,400.00 |
| 0044 | 732-04-19000 | Plastic Pavement Legends and Symbols (SCHOOL CROSSING) | 12 | EACH | 425.00 | 5,100.00 | 400.00 | 4,800.00 |
| 0045 | 735-01-00100 | Mailboxes | 60 | EACH | 1.00 | 60.00 | 1.00 | 60.00 |
| 0046 | 735-02-00100 | Mailbox Supports (Single) | 56 | EACH | 105.00 | 5,880.00 | 100.00 | 5,600.00 |
| 0047 | 735-03-00100 | Mailbox Supports (Double) | 2 | EACH | 130.00 | 260.00 | 130.00 | 260.00 |
| 0048 | 736-09-00100 | Loop Detector | 5,819 | LNFT | 12.10 | 70,409.90 | 12.00 | 69,828.00 |
| 0049 | 740-01-00100 | Construction Layout | 1 | LUMP | 25,000.00 | 25,000.00 | 10,000.00 | 10,000.00 |
| 0050 | 741-11-00100 | Adjusting Water Valve | 8 | EACH | 35.00 | 280.00 | 700.00 | 5,600.00 |
| 0051 | 741-11-00200 | Adjusting Water Valve and Meter Box | 2 | EACH | 35.00 | 70.00 | 500.00 | 1,000.00 |
| 0052 | NS-200-00020 | Cleaning Existing Ditches | 30 | LNFT | 20.00 | 600.00 | 30.00 | 900.00 |
| 0053 | NS-500-00220 | Sawing and Sealing Longitudinal Joints in Asphaltic Concrete Overlay | 62,375 | LNFT | 1.00 | 62,375.00 | 1.00 | 62,375.00 |
| 0054 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphaltic Concrete Overlay | 94,500 | LNFT | 1.00 | 94,500.00 | 1.00 | 94,500.00 |
| 0055 | NS-500-00260 | Sawcuts in Asphaltic Concrete Lifts | 156,875 | LNFT | 0.90 | 141,187.50 | 0.01 | 1,568.75 |
| 0056 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 133,344 | INLF | 0.50 | 66,672.00 | 1.00 | 133,344.00 |
| 0057 | NS-713-00001 | Dynamic Message Sign Unit | 2 | EACH | 20,000.00 | 40,000.00 | 15,000.00 | 30,000.00 |
| ITEM TOTAL (CONSTRUCTION BID) | 4,949,982.25 | 5,844,680.85 | ||||||
| NUMBER OF DAYS BID AT $3000 PER DAY. | 405,000.00 | 600,000.00 | ||||||
| TOTAL BID | 5,354,982.25 | 6,444,680.85 | ||||||